Skip to content
OneCharge logo

Installation & Site Services

From site survey to switch-on — we handle it end to end.

Site survey, design, installation, utility applications, commissioning, and platform setup — plus ongoing maintenance. One team handles every step, from property developers to malls, hotels, and fleet depots.

Huawei DC 240kW split-type EV charger, installed and commissioned

Key features

Site survey & design

We assess the site's electrical capacity and layout, then design the right charger setup before any work starts.

Installation

Installed and wired by our own team, to spec.

Utility applications

We handle the utility paperwork on your behalf — including Low Priority load-management registration where it applies.

Commissioning

Every charger is tested end to end before it goes live.

Platform setup

Every charger and connector configured on OneCharge, ready to accept payments from day one.

Ongoing maintenance

Maintained for the life of the installation.

Installation process

From site survey to switch-on

One team handles every step — site survey, utility filing, installation, through to commissioning

1

Site survey

Our survey team visits the site in person to check available parking, the existing electrical system, and possible cable routes. We also discuss the number of charging points needed, budget, and how the site plans to use the chargers, so we can recommend the right hardware and port count for the location.

2

Deposit & utility filing

Once the design and budget are agreed, the customer pays a first deposit to start the project. We then file the utility application on the site owner's behalf to secure a meter point for the charger — usually the longest-lead step in the whole process, so we start it as early as we can.

3

Installation planning

We plan the installation in detail — cable routing, where the control cabinet will sit, and any surface work needed — then do a final walkthrough to confirm everything still matches the design before agreeing a start date with the site owner.

4

Charger installation

Once the charger arrives on site, our own team installs and wires it according to the plan, coordinating with the building's electrical contractor where needed, so the work gets done with as little disruption to the site as possible.

5

Low Priority test scheduled

For sites that need Low Priority registration, we schedule a load-management test with the utility to confirm the chargers correctly stay within the approved power limit before the site goes live.

6

OneCharge commissioning

Our team runs a full end-to-end test — charger-to-platform communication, payments, and pricing and access configuration — and walks the site owner through how everything works before the charger goes live.

Flexible either way

Already bought and installed your own charger? Connect it to the OneCharge platform directly — you don't have to go through our install team

How it works

Huawei DC 240kW split-type EV charger, installed and commissioned
1

Huawei DC 240kW split-type charger, installed and commissioned

Huawei DC 720kW split-type EV charger installation in Phichit
2

Huawei DC 720kW split-type installation in Phichit

Six Beny 320kW EV chargers installed at Kingkaew (hardware sale)
3

Six Beny 320kW chargers installed at Kingkaew

Huawei DC 240kW split-type EV charger installation at Mint Tower
4

Huawei DC 240kW split-type installation at Mint Tower

Ready to get started with Installation & Site Services?